Massillon's WPA Projects: Street Improvements

Topics:

[ Introduction | Business Improvements | Park Works | School Works | Sewer Works | Street Improvements| Miscellaneous ]

Ali Mercer
Main Ave. W
Resettled fallen curbs
WPA Spent: $938.00
Total Spent: $1,085.00



Ali Mercer
Oberlin Rd. SW
WPA Spent: $3,027.00
Total Spent: $6,577.00



Ali Mercer
Oak Ave. SE
WPA Spent: $10,569.00
Total Spent: $12,825.00



Ali Mercer
16th St. S.E.
WPA Spent: $17,813.00
Total Spent: $18,295.00
 

Additional Projects:


Hills and Dales Rd.
Paving of road.
WPA Spent: $12,001.00
Total Spent: $14,969.00

3rd St. SE
WPA Spent: $1,971.00
Total Spent: $2,164.00
 